BAR BENDING SCHEDULE (BBS) ,1.COLUMN, 2.BEAM BAR CALCULATION

BAR BENDING SCHEDULE (BBS)

BAR BENDING SCHEDULE

Calculation of the total quantity of bars required for completing a construction project or a part of the construction project is called Bar Bending Schedule

The Bar Bending Schedule calculation technique is different for beams, columns, slabs, footings etc.It becomes very important in estimating the cost of the project

as the cost of reinforcement in a construction project has a major part in determining the total cost

In this article, we will be understand the Bar Bending Schedule calculation for Columns,BEAM,

1. COLUMN BAR BENDING SCHEDULE

In this article, we have given the bar bending schedule of columns only for ground floor and it will be very helpful for you to understand

In this post, we are going to explain “How to make bar bending schedule for Column?”

This article will be quite long.

First of all, there are some criteria & assumptions that need to be met while making bar bending schedule for a column. Let’s get started.

Details from the diagram:

  • Thickness of slab is150 mm
  • Floor height is 3.5 m or 3500 mm
  • Footing depth is 400 mm
  • Development Length is 50d
  • Column has 4 numbers of 16 mm dia bars
  • Column has 4 numbers of 20 mm dia bar
  • Stirrup spacing is 10mm @ 150 mm C/C
  • Concrete Cover of Footing is 70 mm

 

Steps for BBS of Column

  • Find the length of Vertical Bar
  • Find out lapping
  • Cutting Length of Stirrups
  • Number of Stirrups
  • Bar Bending Schedul

Step 1 – Find the length of Vertical Bar

To find the cutting length of colum bar

 

First we have to make a calculation according to this drawing

=footing thickness-footing cover-m bar dia-d bar dia+L bend bar length-bend deduction+ug bar +plinth beam hight+floor to beam bottom hight+(roof beam hight-cover+L bend –bend deduction

 

= 0.4-0.07-0.016-0.016+0.3-0.02+0.9+0.5+3.5+

(0.5-0.07+0.30.04)

=6.168

This is the cutting length of vertical bar for column

if total 4 bars of 20mm and 4 bars of 16mm using in

column then we need to make excel sheet showing below:

Step 2 – Find the length of cutting length of Ring

Formula for ring bar calculation:

=(2xlength of column)-(2xcover)+( 2xwidth of column)-(2xcover )-bend deduction+hook length

=(2*0.45)-(2×0.025)+(2*0.25)-(2×0.025)-0.12+0.08

=1.26

 

 

One ring cutting length is 1.26

=(2*0.2)+(2*0.155)-0.12+0.08

=.67

 

Here for 2nd ring size direct taken from autocad .

2nd ring cutting length is 0.67

Hence,the excel sheet is

IMPORTANT POINTS

Always tie the column at the centre of each floor Since the axial loads & internal forces are maxim at top & bottom of the column.

  • Always lap alternate bars
  • Always lap top bar over the bottom bar
  • Try to minimize the lap length and cutting of the bar as much as you can.

BEAM BBS

  • There may be other methods to find out bar bending schedule for Beam. The below method is just a guide. Some people will calculate for each floor, here we discussed the bar bending schedule for a Beam to a whole building at once.

Suppose we have drawing

GIVEN DATA

Clear Span of Beam = 7400 mm

Development Length Ld = 20d (assumption)

Clear Cover on any ends = 25 m

Bottom – 2 numbers of 20⌀ (DIA)

Top – 2 numbers of 20⌀ (DIA)

Mid -2numbers of 12⌀(DIA)

Stirrups spacing –10⌀ (DIA) @ 200mm clear cover

 

 

Beam size -250×500

Find cutting length top bar

Cutting length formula:-

= Span length-clear cove x2+L bend(devolpment length)x2-bend deduction

= 7400-25×2+20xD-2Dx2

=7400-50+400+400-40×2

=7400-50+400+400-80

=8070MM

SIMILARLY FOR BOTH BOTTOM AND MID BAR WILL BE PROCESS THIS IS VERY SIMPLE WAY TO UNDERSTANDING ABOUT TO CALCULATION CUTTING LENGTH OF BEAM BARS.

1 thought on “BAR BENDING SCHEDULE (BBS) ,1.COLUMN, 2.BEAM BAR CALCULATION”

  1. Pingback: Essential AutoCAD Tools for Effective Learning and Design

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top